Pipework – National Retailer

Working onsite in Victoria for a national retailer, the team at CG Systems was responsible for piping three floors of Fan Coils, which we achieved by forming a supplementary plant room on the top floor to provide hydraulic separation from the existing landlord’s supply on the Heating and Chilled systems.

This was certainly one of the more challenging products (with regard to time pressure) we’ve completed but our Engineers have moved along at a phenomenal pace and kept within the allocated schedule, even finishing early on one of the floors. Have a look at the results…

Plant room pipework

Heating pipework

Victoria warehouse pipework

If you’d like further information on our involvement in this project, feel free to contact the CG Systems team on info@cgsystems.cc.

Major Supermarket, Pimlico

In October, we were instructed to carry out works for a major supermarket based in Central London.

Our experienced engineers stripped out four boilers and replaced these with Ideal Tormax 100 boilers, as well as installing a Megaflo 500 litre commercial hot water cylinder.

We used materials including Gebrit Mapress pipe and fittings, as well as Grundfos twin head pumps, which are more reliable and energy-efficient.

Low carbon steel was used for the heating system, which is not only better for the environment but is proven to be a better product due to its corrosion resistance. Stainless steel was used on the gas supply. By using Ideal frame headers and the Gebrit system as opposed to traditional materials, the installation time was substantially improved.

If you’d like further information on our involvement in this project, feel free to contact the CG Systems team on info@cgsystems.cc.